Mallinson delivered a complete in-season reconstruction of the Crown Oil Arena pitch, incorporating drainage, irrigation, pitch-profile construction and hybrid carpet installation.
The works were completed within a tightly controlled Christmas fixture window, maintaining the club’s match schedule throughout delivery.
Rochdale AFC required a complete upgrade of the Crown Oil Arena pitch while protecting its live fixture programme.
The works had to be delivered between scheduled matches, with drainage, irrigation, pitch-profile construction and hybrid carpet installation carefully sequenced within a restricted Christmas programme. Effective coordination and programme control were essential because there was little tolerance for delay between each operation.
Mallinson managed the complete delivery package, coordinating specialist teams, plant and materials around the club’s live operational requirements.
Programme planning around scheduled fixtures
Drainage installation
Irrigation installation
Pitch-profile construction and precision grading
Hybrid carpet system installation
Final surface preparation and handover
Rochdale AFC received a fully reconstructed hybrid playing surface with integrated drainage and irrigation, delivered without interruption to its scheduled match programme.
The project demonstrates Mallinson’s ability to coordinate complex, time-critical stadium works in a live operational environment, with one contractor accountable for the complete construction package.