Mallinson delivered the full reconstruction of the Deepdale stadium pitch, including earthworks, drainage upgrades, pitch-profile construction, irrigation and heating coordination, seeding and stitched-hybrid reinforcement.
Approximately 5,000 tonnes of material were imported, with the pitch constructed and seeded within a tightly controlled close-season programme.
Deepdale required a complete stadium-pitch reconstruction within a fixed close-season window, while retaining sufficient time for establishment before the new surface returned to play.
The programme involved approximately 5,000 tonnes of imported material, drainage upgrades, coordination around irrigation and undersoil-heating services, pitch-profile construction, seeding and hybrid reinforcement. Each operation had to be completed in sequence, with limited tolerance for delay or rework.
Mallinson managed the complete reconstruction package, coordinating earthworks, specialist systems, pitch construction and establishment through one controlled programme.
Removal of the existing playing surface and pitch profile
Earthworks and formation preparation
Drainage upgrades
Coordination with irrigation and undersoil-heating systems
Construction and precision grading of the new pitch profile
Rootzone installation and seeding
Stitched-hybrid reinforcement
Quality-control inspections and surface preparation
Establishment and preparation for handover
The completed works delivered a fully reconstructed GrassMaster stitched-hybrid playing surface, supported by upgraded drainage and a newly constructed pitch profile. The pitch was seeded on programme, protecting the required establishment period before returning to use.
By coordinating major material movements, earthworks, specialist services, seeding and hybrid reinforcement through one delivery team, Mallinson reduced interface risk and maintained control of the close-season programme.
Speak to Mallinson about construction, renovation or specialist systems for your facility.